Credit committee paperSection 07 / 07

07 · Risks & terms

Key risks and mitigants

Each risk is matched to a structural control. The figures recalculate with the scenario so the committee can see each mitigant hold.

Exhibit 7.1 · Risk register

Each risk, its structural control and the live test

R1

Transnet rail performance

At 60% of planned railings, Lancaster's IRR rises to 24.7% (lower drawn, fee intact) and Arnot still nets R136m. Allocation is confirmed before first drawdown.

24.7% IRR at 60% railings

R2

Coal price and FX

Breakeven $98/t or R13.44/$. Cargo cover stays at 2.2x even with a 30% price fall. A forward FX cover option is offered on each LC.

2.2x cover after −30% price

R3

Buyer payment delay

Payment only by irrevocable LC at sight, confirmed by an SA bank. A draw-stop applies while a prior tranche is unpaid.

Peak capped at R44.3m

R4

Quality and spec rejection

An independent inspector (SGS or Bureau Veritas) samples at the siding and at loading; the CoQ is an LC document.

Two-point inspection

R5

Title and security

Pledge over coal in transit, cession of offtake and LC proceeds, and a Lancaster-controlled collection account.

R100.3m cargo per cycle

Bottom line

A price fall erodes Arnot's profit before it reaches Lancaster's security. Each tranche is covered by cargo and repaid from the LC.

Cargo cover
3.1x
Headroom
R5.7m

Exhibit 7.2 · Indicative terms

Facility terms summary

Borrower
Arnot OpCo
Lender
Lancaster Group
Facility
R50m revolving trade finance
Tenor
12 months
Purpose
Pre-finance of road and rail logistics invoices for RB2 exports, Arnot → Sunberry → Durban (FOB)
Advance rate
80% of road and rail invoices
Pricing
Prime (10.75%) + 4.00% = 14.75%
Raising fee
2.0% of limit, upfront (R1.00m)
Repayment
Each tranche from irrevocable LC proceeds at sight into the collection account
Security
Pledge over coal in transit; cession of offtake and LC proceeds; Lancaster-controlled collection account
Covenant
Draw-stop: no new cycle may start while a prior tranche is unpaid if it would take exposure over the limit
Asset
51.3 Mt ROM reserves; mining right valid to 2039; ungeared balance sheet; existing Eskom CSA

Note · Terms reflect the proposal and update with the current scenario. Final terms are subject to the facility agreement.

Exhibit 7.3 · Committee review

Conditions and review checklist

Tick items as they are confirmed. Progress is saved in this browser only.

0 of 8 confirmed